HIT Park Data Center FAQ

Project Background

What is the HIT Park?

The Heartland Innovative Technology Park (HIT Park) is a 280-acre industrial and technology development site owned by the Prince Edward County Industrial Development Authority (IDA). The property was acquired in 2020 and has been the focus of more than a decade of economic development planning, infrastructure engineering, grant funding, and site readiness efforts designed to attract major private-sector investment. The site is located east of Farmville, has major electric transmission infrastructure, and is near regional fiber networks.

 

What is being proposed?

The County and IDA have entered into agreements with AVAIO Digital Partners II, LLC, a data center developer, regarding the potential purchase and development of the HIT Park as a data center campus. The project remains in the due diligence and development planning phase. No site plans, building permits, or construction plans have been submitted to Prince Edward County at this time.

 

How large could the project be?

The agreements contemplate development of a multi-building data center campus on approximately 280 acres. Publicly available project documents reference up to 300 megawatts (MW) of electric service and multiple data center buildings. However, final project size, building locations, and development phasing have not yet been submitted for review.

 

Who is AVAIO?

AVAIO Digital Partners (https://www.avaiodigital.com/) is a data center developer and operator that identifies, acquires, and develops sites for large-scale data center projects.  Other AVAIO project sites in Virginia include Appomattox County and Caroline County.

 

Planning & Approval Process

When did Prince Edward County begin planning for data center development?

Prince Edward County first identified data centers as a targeted economic development opportunity in 2014 and began actively evaluating opportunities with regional and state economic development partners in 2019. The County subsequently acquired the HIT Park property, amended its zoning regulations after public notices and public hearings, pursued infrastructure grants, and conducted engineering studies to prepare the site for future development.

 

Is data center development allowed at the HIT Park?

Yes. In July 2020, the County amended its Zoning Ordinance to define and permit data centers as a by-right use within the C-1 Commercial Zoning District. The HIT Park was rezoned to C-1 Commercial following public notices and public hearings before both the Planning Commission and Board of Supervisors.

 

Has the County approved a specific data center project?

No. While data center use is permitted on the property, no site plans, building permits, or construction plans have been submitted or approved.

 

Will there be additional public review?

Not in the form of additional public hearings or votes by the Planning Commission or Board of Supervisors.  Because data centers are already a permitted use within the HIT Park, future development proposals would proceed through the administrative review process established by County ordinance.

That does not mean projects avoid review. Any development must still comply with all applicable local, state, and federal requirements, including site plan review, building permits, environmental permits, stormwater management requirements, utility approvals, and other technical standards. Those reviews are conducted by County staff and regulatory agencies to ensure compliance before construction can occur.

Citizens will continue to have access to public records and information regarding the project as required by law.

 

Water & Environmental Issuses

Where would water for the project come from?

Potential water sources could include the Town of Farmville water system or Prince Edward County's Sandy River Reservoir system. The final source will depend on the requirements of the eventual end users and the approved development plans.

 

How much water will the project use?

That information is not currently known. Water demand depends heavily on the cooling technology ultimately selected and the needs of the future tenant(s). No detailed engineering plans have been submitted.  However, based on technology trends and best practices, closed loop systems are likely to be included in these plans.

 

What type of cooling system will be used?

No cooling system has been proposed at this time. Modern data centers utilize a variety of cooling technologies, including air-cooled, liquid-cooled, and hybrid systems.

 

What happens during drought conditions?

Any water withdrawals would be subject to state regulations and permit conditions. The Virginia Department of Environmental Quality regulates water withdrawals and drought management requirements.

 

Will environmental permits be required?

Yes. Any future development must comply with all applicable local, state, and federal environmental regulations, including stormwater, erosion and sediment control, wetlands, and other environmental requirements.

 

Electric Power & Utilities

Why was the HIT Park selected for data center recruitment?

The site possesses several characteristics sought by data center developers, including access to major high voltage electric transmission infrastructure, fiber connectivity, large acreage, buffering from residential development, and transportation access.

 

How much power could the project require?

Project documents contemplate up to 300 MW of electrical service. Actual demand will depend on the final design and occupancy of the campus.  The final power allocation is determined by Dominion Energy.

 

Will new transmission lines be required?

At this time, Prince Edward County has not received any utility construction plans or other information about additional transmission lines. Any required electric infrastructure improvements would be evaluated and determined through Dominion Energy's interconnection and service planning process.

 

Will Prince Edward County taxpayers pay for electric infrastructure upgrades?

Generally, customer-specific electric infrastructure required to serve a development is the responsibility of the customer and utility under applicable service agreements.

 

Has Dominion Energy indicated that power is available?

A load request and utility review process has been initiated as part of project due diligence. Final utility commitments, construction schedules, and infrastructure requirements will be determined through Dominion Energy's formal review process.

 

Traffic & Transportation

Will the project increase traffic?

Construction activity would generate temporary increases in traffic. Operational traffic associated with data centers is typically lower than most industrial or commercial facilities because data centers generally employ fewer workers per square foot.

 

Will the project require road improvements?

Any future development proposal will be reviewed to determine its transportation impacts and identify any necessary roadway improvements.

The County recognizes that Persimmon Tree Fork Road serves as the primary access route to the HIT Park and that transportation infrastructure must keep pace with development. To proactively address future needs, Prince Edward County recently secured grant funding from the Virginia Tobacco Region Revitalization Commission to complete a transportation study and engineering plans for improvements to Persimmon Tree Fork Road and related access infrastructure serving the HIT Park area.

The purpose of this effort is to identify needed roadway, safety, and access improvements before significant development occurs and to position the County to pursue additional state and federal transportation funding opportunities.

Any future site plan submitted for the project would also be reviewed by the Virginia Department of Transportation (VDOT).

Because data centers generally have relatively few daily employees compared to manufacturing plants, distribution centers, or retail developments of similar size, operational traffic volumes are typically much lower once construction is complete. The greatest traffic impacts generally occur during the construction phase and are addressed through the site development review process.

 

Noise, Appearance, & Community Impacts

What will the buildings look like?

No architectural plans have been submitted.

 

Will the project create noise?

Any future development must comply with applicable County regulations and development standards. The County is also evaluating additional supplemental development standards and best management practices specific to data center development.

 

How will neighboring properties be protected?

The HIT Park is subject to recorded Protective Covenants, Conditions, and Restrictions designed to promote high-quality development, coordinated site planning, and compatible land uses with minimal impacts on surrounding areas.

 

Economic Development & Jobs

How will the HIT Park project benefit Prince Edward County's economy?

The proposed HIT Park development represents one of the largest private capital investment opportunities in Prince Edward County's history. In addition to generating significant local tax revenue, the project has the strong potential to create both direct and indirect employment opportunities during construction and operation.  The project also has the potential to attract additional commercial investment in the community.

Data centers employ a wide range of skilled workers, including electricians, HVAC technicians, facility engineers, network specialists, security personnel, operations managers, and maintenance staff. Across Virginia, data centers directly support thousands of high-paying technology and skilled trades jobs.

Equally important are the indirect and induced jobs supported by data center development. According to a 2026 economic impact analysis prepared by Mangum Economics for the Northern Virginia Technology Council, every operational data center job supports approximately two additional jobs elsewhere in the economy through suppliers, contractors, service providers, restaurants, retail businesses, construction firms, transportation companies, and other local businesses. Statewide, data centers support more than 112,000 jobs when both direct and indirect impacts are considered.

Construction of a large data center campus also creates substantial demand for skilled trades, including electricians, pipefitters, welders, equipment operators, concrete contractors, and other construction professionals. Virginia data center construction projects supported approximately 36,700 construction jobs in 2025 alone.

For Prince Edward County, these impacts could translate into:

  • Long-term technology and facilities management jobs;
  • Construction employment lasting several years;
  • Increased demand for local contractors and suppliers;
  • New opportunities for local restaurants, hotels, retailers, and service businesses;
  • Expanded workforce development partnerships with Longwood University, Hampden-Sydney College, Southside Virginia Community College, and local schools; and
  • Additional tax revenue to support public services and help maintain competitive tax rates.

As with any economic development project, the exact number of jobs and investment will depend on the final development plan submitted by the property owner.

 

What is the County's return on investment in the HIT Park?

The HIT Park represents one of the most significant economic development investments ever undertaken by Prince Edward County and the Industrial Development Authority (IDA). The property was acquired in 2020 for approximately $1.5 million and is currently under contract for sale at $12.3 million. If the transaction is completed, the sale would generate a substantial return on the original investment and provide resources that can be reinvested into future economic development initiatives, infrastructure improvements, and other public priorities.

How much will AVAIO and/or its tenants invest in the HIT Park?

Equally important is the level of private investment anticipated as a result of the project. Based on information provided by the developer, AVAIO is expected to invest approximately $2.4 billion to construct the data center campus and supporting infrastructure. The ultimate tenant or operator is expected to invest an additional $4.0 billion or more in servers, networking equipment, and other technology infrastructure necessary to operate the facility.

Taken together, the project has the potential to leverage a $1.5 million land acquisition into more than $6 billion in private capital investment, creating a significant expansion of the local tax base and generating long-term revenue to support public services, infrastructure, schools, and economic development opportunities throughout Prince Edward County.

As with any development project, actual investment levels, tax revenues, and economic impacts will depend on the final scope and timing of development.

 

Public Transparency

Why are some questions difficult to answer today?

Many details frequently discussed by the public—including water use, cooling systems, utility upgrades, traffic volumes, building designs, and tenant identity—cannot be determined until detailed engineering and development plans are submitted.

 

Where can I find project information?

Prince Edward County will continue to make publicly available information accessible through its website, Board meeting materials, public records, and future project updates as additional information becomes available.

 

How can I ask questions?

Residents may contact the County Administrator's Office, Community Development Department, or attend public meetings of the Board of Supervisors and Planning Commission.

 

Myth vs. Facts

Myth: The County recently changed the zoning to allow a data center at the HIT Park.

Fact: Data centers have been a permitted use in the C-1 Commercial Zoning District since July 2020. At that time, the County amended its Zoning Ordinance to define and permit data centers and rezoned the HIT Park property from A-2 Agricultural to C-1 Commercial following public notices and public hearings before both the Planning Commission and Board of Supervisors.

 

Myth: The County secretly approved a data center project.

Fact: No site plan, building permit, or construction plans have been submitted or approved by Prince Edward County. While the County and Industrial Development Authority have entered into agreements regarding the potential sale and development of the property, future development remains subject to applicable local, state, and federal permitting requirements and subject to receiving an adequate power allocation and other necessary decisions from Dominion Energy.

 

Myth: Construction is about to begin.

Fact: No construction plans have been submitted for review and no construction permits have been issued. Before any development can occur, detailed engineering plans, utility plans, stormwater plans, and building permits must be reviewed and approved.

 

Myth: The County already knows exactly how much water the project will use.

Fact: Water usage depends on the specific data center design, cooling technology, and end user requirements. Because no development plans have been submitted, the County does not yet know the final water demand for the project.

 

Myth: The project will use all of the County's water supply.

Fact: No evidence currently supports this claim. Any water service would be subject to engineering review, state permitting requirements, and available system capacity. The County's Sandy River Reservoir was designed as a long-term water supply asset, and any withdrawals would be regulated by the Virginia Department of Environmental Quality.

 

Myth: Data centers always consume enormous amounts of water.

Fact: Water use varies significantly depending on cooling technology. Some modern data centers utilize air-cooled systems or closed-loop cooling systems that substantially reduce water consumption compared to traditional cooling methods. The cooling technology for the HIT Park project has not yet been determined.

 

Myth: Dominion Energy must build new 300 kV transmission lines for this project.

Fact: Electric service requirements and infrastructure needs are determined by Dominion Energy through its utility planning and interconnection review process. The HIT Park was intentionally selected, in part, because it is located adjacent to existing high-voltage transmission infrastructure. Any additional upgrades that may be required will be identified through Dominion's formal engineering review.

 

Myth: Local taxpayers will pay for electric infrastructure upgrades.

Fact: Customer-specific electric infrastructure associated with development projects is generally funded by the developer and utility under applicable service agreements. The County does not anticipate funding private electric infrastructure improvements for the project.

 

Myth: The County is giving the property away.

Fact: The HIT Park property is under contract for sale based upon negotiated terms approved by the Industrial Development Authority and Board of Supervisors. The agreements include purchase payments, infrastructure commitments, and economic development objectives intended to benefit the community.  The County's $1.5 million acquisition of the HIT Park has the potential to generate a $12.3 million land sale and leverage more than $6 billion in private investment, representing one of the largest economic development returns on investment in Prince Edward County's history.   

 

Myth: Data centers do not create jobs.

Fact: Data centers create both construction and permanent jobs. While they typically employ fewer people than manufacturing facilities of comparable size, they often provide highly skilled technical, facilities management, security, and support positions. In addition, construction of a data center campus can generate hundreds of temporary construction jobs over multiple years.  Plus, data center projects typically attract additional businesses and job opportunities to the communities in which they locate.

 

Myth: Data centers provide little benefit to the community.

Fact: Communities pursue data center development because of the significant tax revenue generated by capital investment in buildings and equipment. Those revenues help fund schools, public safety, infrastructure, recreation, and other local government services. The County's goal is to ensure that any development provides long-term benefits that outweigh potential impacts.

 

Myth: The County knows who the final tenant will be and is keeping it secret.

Fact: At this time, the County has not been informed of any final end user or tenant for the site. In many cases, data center developers construct facilities that are later leased to one or more technology companies, retailers and banks, streaming and other entertainment services, cloud service providers, government agencies, or other users.

Myth: Residents will not have an opportunity to learn about future development plans.

Fact: As additional information becomes available and development applications are submitted, the County will continue to provide information through public meetings, Board agendas, public records, and other communication channels. The County remains committed to transparency and public engagement throughout the development process.

 

Myth: The County is ignoring citizen concerns.

Fact: County staff and elected officials have spent considerable time meeting with residents, answering questions, reviewing information from other Virginia localities, consulting with utilities and industry experts, and evaluating potential development standards. The County recognizes that projects of this scale generate questions and believes those questions deserve thoughtful, factual answers.

Myth: "Prince Edward County suddenly decided to pursue a data center."

Fact: The HIT Park represents more than a decade of economic development planning. Data centers were first identified as a target industry in 2014, and since then the County has invested in land acquisition, infrastructure planning, state site certification efforts, grant funding, utility studies, marketing, and due diligence to position the property for large-scale economic development opportunities. This project is the result of a long-term strategy, not a recent decision.

 

Myth: Members of the Industrial Development Authority (IDA), Planning Commission, or Board of Supervisors are personally benefiting from the proposed HIT Park data center project.

Fact: No member of the Prince Edward County Board of Supervisors, Planning Commission, or Industrial Development Authority is receiving compensation, ownership interests, profit-sharing, commissions, or other financial benefits as a result of the proposed development of the HIT Park.

Virginia law requires public officials to disclose potential conflicts of interest and, when necessary, recuse themselves from participating in matters where a financial interest exists. The County is not aware of any such conflicts related to the proposed project.

The Board of Supervisors, Planning Commission, and Industrial Development Authority evaluate economic development opportunities based on what they believe is in the best interest of Prince Edward County and its citizens. Their decisions are made through public meetings, public records, and established legal processes designed to ensure transparency and accountability.

Because the HIT Park is already zoned to allow data centers, by right, future permit applications and site plans would be reviewed through the County's standard administrative review process. Those reviews are conducted by County staff and technical professionals, including engineers, attorneys, and consultants, to ensure compliance with applicable laws, ordinances, and development standards. These professionals provide technical advice and recommendations but do not establish County policy or make legislative land-use decisions.

 

Documents:

HIT Park Annual Economic and Fiscal Contribution to Prince Edward County(PDF, 315KB)

*Note: As additional questions and concerns arise, the County will expand these FAQs. This site will also provide updates on the project, as they become available.